Fort Bragg Multi-Use

U.S. Army · Fayetteville, NC

Phase
Manufacturing
Progress
11%
Contract
$2.4M
Square feet
120,000
Target
just now
Change orders
$0

Pipeline

1 of 7 phases
Manufacturing
40%
Shipping
0%
Base prep
0%
Turf install
0%
Infill
0%
Striping
0%
Complete
0%

Tasks (current phase)

4
  • Confirm specs with mill
  • Schedule production slot
  • QA inspection sample
  • Release to shipping

Milestones

4
  1. Contract NTP
    Apr 26, 2026 · 6d ago
    complete
  2. Mill production complete
    Jun 9, 2026 · just now
    upcoming
  3. Site mobilization
    Jul 1, 2026 · just now
    upcoming
  4. Substantial completion
    Aug 10, 2026 · just now
    upcoming

Change orders

0
No change orders.

Documents

1
  • Federal contract W912HN-26-C-0042.pdf
    contract · 3.1 MB · uploaded 9d ago by JS