Project portal
Live
U.S. Army

Fort Bragg Multi-Use

Fayetteville, NCMulti-use120,000 sq ft
Where things stand
11%
complete
Current phase
Manufacturing
Target completion October 1, 2026 (just now)
ManufacturingShippingBaseTurfInfillStripingComplete

Phase progress

  1. Manufacturing
    40%
  2. Shipping
    0%
  3. Base prep
    0%
  4. Turf install
    0%
  5. Infill
    0%
  6. Striping
    0%
  7. Complete
    0%

Key dates

  1. Contract NTP
    Jun 7, 2026 · 6d ago
    complete
  2. Mill production complete
    Jul 21, 2026 · just now
    upcoming
  3. Site mobilization
    Aug 12, 2026 · just now
    upcoming
  4. Substantial completion
    Sep 21, 2026 · just now
    upcoming

Shared documents

  • Federal contract W912HN-26-C-0042.pdf
    contract · 3.1 MB

Your project manager

JS
J. Savoca
Project manager