Maple Park Soccer Complex

City of Bellevue · Bellevue, WA

Phase
Base prep
Progress
28%
Contract
$3.9M
Square feet
240,000
Target
just now
Change orders
$0

Pipeline

3 of 7 phases
Manufacturing
100%
Shipping
60%
Base prep
45%
Turf install
0%
Infill
0%
Striping
0%
Complete
0%

Tasks (current phase)

5
  • Site survey + grade check
  • Excavate + haul-off
  • Aggregate base install
  • Drainage tie-in
  • Compaction + final grade

Milestones

4
  1. NTP issued
    Apr 14, 2026 · 18d ago
    complete
  2. Base substantial completion
    May 16, 2026 · just now
    upcoming
  3. Turf delivery
    May 23, 2026 · just now
    upcoming
  4. Final inspection
    Jul 1, 2026 · just now
    upcoming

Change orders

0
No change orders.