Project portal
Live
City of Bellevue

Maple Park Soccer Complex

Bellevue, WASoccer x3240,000 sq ft
Where things stand
28%
complete
Current phase
Base prep
Target completion August 17, 2026 (just now)
ManufacturingShippingBaseTurfInfillStripingComplete

Phase progress

  1. Manufacturing
    100%
  2. Shipping
    60%
  3. Base prep
    45%
  4. Turf install
    0%
  5. Infill
    0%
  6. Striping
    0%
  7. Complete
    0%

Key dates

  1. NTP issued
    May 26, 2026 · 18d ago
    complete
  2. Base substantial completion
    Jun 27, 2026 · just now
    upcoming
  3. Turf delivery
    Jul 4, 2026 · just now
    upcoming
  4. Final inspection
    Aug 12, 2026 · just now
    upcoming

Shared documents

  • Master contract — Bellevue.pdf
    contract · 2.1 MB
  • Drainage spec.pdf
    spec · 0.9 MB

Your project manager

JS
J. Savoca
Project manager