Lincoln HS Stadium
Lincoln Unified School District · Stockton, CA
Search
K
All projects
Open client portal
Update status
Phase
Turf install
Progress
62%
Contract
$1.5M
Square feet
80,000
Target
just now
Change orders
+$18.5K
Pipeline
4 of 7 phases
Manufacturing
100%
Shipping
100%
Base prep
100%
Turf install
55%
Infill
0%
Striping
0%
Complete
0%
Tasks (current phase)
5
Task
Layout + cut panels
R. Diaz
12d ago
Seam + glue (north end)
R. Diaz
5d ago
Seam + glue (south end)
R. Diaz
just now
Inlay logos + end zones
M. Park
just now
Border anchor + nailing
R. Diaz
just now
Milestones
5
Site mobilization
Mar 22, 2026
· 1mo ago
complete
Base certification
Apr 14, 2026
· 18d ago
complete
Turf substantial completion
May 14, 2026
· just now
upcoming
GMAX cert
May 20, 2026
· just now
upcoming
Final acceptance
May 24, 2026
· just now
upcoming
Change orders
2
Submit
CO-001
Drainage tie-in upgrade per inspector
+$18.5K
+3d
approved
CO-002
Add school logo inlay to south end
+$6.2K
+1d
pending
Documents
4
Upload
Contract — Lincoln USD signed.pdf
contract · 1.2 MB · uploaded 2mo ago by JS
Field spec drawing rev3.pdf
drawing · 4.7 MB · uploaded 1mo ago by JS
City permit BR-2026-1142.pdf
permit · 0.3 MB · uploaded 1mo ago by RD
Base inspection photos.zip
photo · 18.0 MB · uploaded 18d ago by RD