Lincoln HS Stadium
Lincoln Unified School District · Stockton, CA
Phase
Turf install
Progress
62%
Contract
$1.5M
Open issues
0
Punch open
0
Change orders
+$18.5K
Phases
Step 4 of 7
Tasks (current phase)
5Milestones
5- completeSite mobilizationJun 24, 2026 · 1mo ago
- completeBase certificationJul 17, 2026 · 18d ago
- upcomingTurf substantial completionAug 16, 2026 · just now
- upcomingGMAX certAug 22, 2026 · just now
- upcomingFinal acceptanceAug 26, 2026 · just now
Change orders
2- CO-001Drainage tie-in upgrade per inspector+$18.5K+3dapproved
- CO-002Add school logo inlay to south end+$6.2K+1dpending
Documents
4- Contract — Lincoln USD signed.pdfcontract · 1.2 MB · uploaded 2mo ago by JS
- Field spec drawing rev3.pdfdrawing · 4.7 MB · uploaded 1mo ago by JS
- City permit BR-2026-1142.pdfpermit · 0.3 MB · uploaded 1mo ago by RD
- Base inspection photos.zipphoto · 18.0 MB · uploaded 18d ago by RD
Site photos
7Turf install
Hash marks aligned, south sideline
2d ago
Turf install
Panels laid, north end zone seamed
6d ago
Turf install
Turf rolls delivered to site
14d ago
Base prep
Compaction inspection passed
18d ago
Base prep
Aggregate base laid, north half
24d ago
Base prep
Excavation complete, west end
1mo ago
Base prep
Site mobilization — equipment staged
1mo ago
Daily logs
0No logs yet. Log each day to share progress with your client and prove warranty compliance.
Issues
0No issues logged. Track weather delays, sub no-shows, material shortages here.
Punch list (QA)
0No punch items. Add one before final acceptance.