Lincoln HS Stadium

Lincoln Unified School District · Stockton, CA

Phase
Turf install
Progress
62%
Contract
$1.5M
Open issues
0
Punch open
0
Change orders
+$18.5K

Phases

Step 4 of 7

Tasks (current phase)

5

Milestones

5
  1. Site mobilization
    Jun 24, 2026 · 1mo ago
    complete
  2. Base certification
    Jul 17, 2026 · 18d ago
    complete
  3. Turf substantial completion
    Aug 16, 2026 · just now
    upcoming
  4. GMAX cert
    Aug 22, 2026 · just now
    upcoming
  5. Final acceptance
    Aug 26, 2026 · just now
    upcoming

Change orders

2
  • CO-001Drainage tie-in upgrade per inspector+$18.5K+3dapproved
  • CO-002Add school logo inlay to south end+$6.2K+1dpending

Documents

4
  • Contract — Lincoln USD signed.pdf
    contract · 1.2 MB · uploaded 2mo ago by JS
  • Field spec drawing rev3.pdf
    drawing · 4.7 MB · uploaded 1mo ago by JS
  • City permit BR-2026-1142.pdf
    permit · 0.3 MB · uploaded 1mo ago by RD
  • Base inspection photos.zip
    photo · 18.0 MB · uploaded 18d ago by RD

Site photos

7
Turf install
Hash marks aligned, south sideline
2d ago
Turf install
Panels laid, north end zone seamed
6d ago
Turf install
Turf rolls delivered to site
14d ago
Base prep
Compaction inspection passed
18d ago
Base prep
Aggregate base laid, north half
24d ago
Base prep
Excavation complete, west end
1mo ago
Base prep
Site mobilization — equipment staged
1mo ago

Daily logs

0
No logs yet. Log each day to share progress with your client and prove warranty compliance.

Issues

0
No issues logged. Track weather delays, sub no-shows, material shortages here.

Punch list (QA)

0
No punch items. Add one before final acceptance.