Lincoln HS Stadium

Lincoln Unified School District · Stockton, CA

Phase
Turf install
Progress
62%
Contract
$1.5M
Square feet
80,000
Target
just now
Change orders
+$18.5K

Pipeline

4 of 7 phases
Manufacturing
100%
Shipping
100%
Base prep
100%
Turf install
55%
Infill
0%
Striping
0%
Complete
0%

Tasks (current phase)

5
  • Layout + cut panelsR. Diaz12d ago
  • Seam + glue (north end)R. Diaz5d ago
  • Seam + glue (south end)R. Diazjust now
  • Inlay logos + end zonesM. Parkjust now
  • Border anchor + nailingR. Diazjust now

Milestones

5
  1. Site mobilization
    Mar 22, 2026 · 1mo ago
    complete
  2. Base certification
    Apr 14, 2026 · 18d ago
    complete
  3. Turf substantial completion
    May 14, 2026 · just now
    upcoming
  4. GMAX cert
    May 20, 2026 · just now
    upcoming
  5. Final acceptance
    May 24, 2026 · just now
    upcoming

Change orders

2
  • CO-001Drainage tie-in upgrade per inspector+$18.5K+3dapproved
  • CO-002Add school logo inlay to south end+$6.2K+1dpending

Documents

4
  • Contract — Lincoln USD signed.pdf
    contract · 1.2 MB · uploaded 2mo ago by JS
  • Field spec drawing rev3.pdf
    drawing · 4.7 MB · uploaded 1mo ago by JS
  • City permit BR-2026-1142.pdf
    permit · 0.3 MB · uploaded 1mo ago by RD
  • Base inspection photos.zip
    photo · 18.0 MB · uploaded 18d ago by RD