Lincoln Unified School District
Lincoln HS Stadium
Stockton, CAFootball / Multi-use80,000 sq ft
Where things stand
62%
complete
Current phase
Turf install
Target completion August 26, 2026 (just now)
ManufacturingShippingBaseTurfInfillStripingComplete
Phase progress
- Manufacturing100%
- Shipping100%
- Base prep100%
- Turf install55%
- Infill0%
- Striping0%
- Complete0%
Key dates
- completeSite mobilizationJun 24, 2026 · 1mo ago
- completeBase certificationJul 17, 2026 · 18d ago
- upcomingTurf substantial completionAug 16, 2026 · just now
- upcomingGMAX certAug 22, 2026 · just now
- upcomingFinal acceptanceAug 26, 2026 · just now
Site photos
7 updatesTurf install
Hash marks aligned, south sideline
2d ago · 8/2/2026
Turf install
Panels laid, north end zone seamed
6d ago · 7/29/2026
Turf install
Turf rolls delivered to site
14d ago · 7/21/2026
Base prep
Compaction inspection passed
18d ago · 7/17/2026
Base prep
Aggregate base laid, north half
24d ago · 7/11/2026
Base prep
Excavation complete, west end
1mo ago · 7/3/2026
Base prep
Site mobilization — equipment staged
1mo ago · 6/25/2026
Shared documents
- Contract — Lincoln USD signed.pdfcontract · 1.2 MB
- Field spec drawing rev3.pdfdrawing · 4.7 MB
- City permit BR-2026-1142.pdfpermit · 0.3 MB
Your project manager
JS