Project portal
Live
Lincoln Unified School District

Lincoln HS Stadium

Stockton, CAFootball / Multi-use80,000 sq ft
Where things stand
62%
complete
Current phase
Turf install
Target completion August 26, 2026 (just now)
ManufacturingShippingBaseTurfInfillStripingComplete

Phase progress

  1. Manufacturing
    100%
  2. Shipping
    100%
  3. Base prep
    100%
  4. Turf install
    55%
  5. Infill
    0%
  6. Striping
    0%
  7. Complete
    0%

Key dates

  1. Site mobilization
    Jun 24, 2026 · 1mo ago
    complete
  2. Base certification
    Jul 17, 2026 · 18d ago
    complete
  3. Turf substantial completion
    Aug 16, 2026 · just now
    upcoming
  4. GMAX cert
    Aug 22, 2026 · just now
    upcoming
  5. Final acceptance
    Aug 26, 2026 · just now
    upcoming

Site photos

7 updates
Turf install
Hash marks aligned, south sideline
2d ago · 8/2/2026
Turf install
Panels laid, north end zone seamed
6d ago · 7/29/2026
Turf install
Turf rolls delivered to site
14d ago · 7/21/2026
Base prep
Compaction inspection passed
18d ago · 7/17/2026
Base prep
Aggregate base laid, north half
24d ago · 7/11/2026
Base prep
Excavation complete, west end
1mo ago · 7/3/2026
Base prep
Site mobilization — equipment staged
1mo ago · 6/25/2026

Shared documents

  • Contract — Lincoln USD signed.pdf
    contract · 1.2 MB
  • Field spec drawing rev3.pdf
    drawing · 4.7 MB
  • City permit BR-2026-1142.pdf
    permit · 0.3 MB

Your project manager

JS