SUPPLY · PRODUCTION

Plant Schedule + Capacity + Production Risk

Production runs by line, utilization, QA status. The plant calendar that protects every install date.
Demo data· MES connector
Runs in flight
1
Scheduled (next 30d)
3
Overbooked lines
1
of 3 plant lines
Active risks
3
2 high
01Plant Schedule · Next 30 days
7 runs
RunProjectSystemLineSqftStartCompleteQAStatus
PR-2026-024Frisco ISD multi-field rolloutGameDay XP-GLine A80kMay 14May 21pendingin-progress
PR-2026-025Round Rock ISDGameDay XP-GLine B78kMay 19May 26scheduled
PR-2026-026Plano West HSRootZoneLine A80kMay 28Jun 03scheduled
PR-2026-027Mansfield ISD (custom logo)GameDay XP-GLine C80kJun 02Jun 11material-hold
PR-2026-028U.S. Naval Academy renewalPro-grade FBLine A95kJun 09Jun 17scheduled
PR-2026-022Lawrenceville SchoolGameDay XP-GLine B78kApr 29May 05passedcomplete
PR-2026-023Western Michigan U practiceRootZoneLine A75kMay 06May 12passedcomplete
02Capacity Planning
3 plant lines
Line A — main
106%255k / 240k
OVERBOOKED
Line B — secondary
88%158k / 180k
Line C — custom work
89%80k / 90k
03Production Risk
3 active
Line A overbookedhigh
106% util — 1 run must shift to Line B or push 1wk
Owner: M. Reyes (Plant Mgr)
Slit-film inventoryhigh
40k lbs on hand of 165k needed — TenCate confirmation pending
Owner: K. Tran (Purchasing)
Custom logo coatingmed
Mansfield logo work waiting on supplier — 6wk LT
Owner: K. Tran (Purchasing)